Harris Search and Rescue Robot
Project Name | Harris Search and Rescue Robot | |
---|---|---|
Team Members and Email Addresses | Tyler Culp | [email protected] |
Milton Stafford | [email protected] | |
Devin Martinez | [email protected] | |
Faculty Sponsor | Philip Chan |
First Semester
Plan (Aug 31) | Plan | Presentation |
---|---|
Milestone 1 (Sep 28) | A-Spec | Allocation | CONOPS | Cost | Test | Business Events | Presentation | Progress Evaluation |
Milestone 2 (Oct 19) | SDR | System Risks | CSFs & TPMs | Context Diagram | Presentation | Progress Evaluation |
Milestone 3 (Nov 23) | PDR | Software Interfaces | Software/Hardware Interfaces | Presentation | Progress Evaluation |
Second Semester
Plan (Jan 25) | Plan | Presentation |
---|---|
Milestone 4 (Feb 22) | Internal SWI | Message Specification | SW Requirements | Presentation | Progress Evaluation |
Milestone 5 (Mar 21) | Poster | Presentation | Progress Evaluation | Internal Interfaces | Message Specification | CDR |
Milestone 6 (Apr 18) | Technical User Manual | End-User Manual | Demo Videos | Presentation | Progress Evaluation |